Ready for testing!
The construction of the new test cell facilities started in October 2017. With this expansion, the current test cell setup will be doubled in order to accommodate the growing turbocharger market. The new building will include a workshop and validation building and new hot gas stands and engine benches.
Step 1:
The planned location of the new test cells before construction was started.
It was added on to factory 4, which was built in 2004.
			Step 2:
December 2017: The wall of the connecting factory is dismantled and the asphalt is removed
			Step 3:
January 2018: The groundwork of building the basement
			Step 4:
February– March 2018: Preparations for pouring the concrete for the foundation
			Step 5:
May 2018: The steel structure is assembled
			Step 6:
June 2018: Placement of inner walls
			Step 7:
July 2018: Placement of outer walls
			Step 8:
July 2018: The roof is constructed
			Step 9:
August 2018: The windows are applied
			Step 10:
September – December 2018: The interior of the test cell facilities are made
			
					

